The envelope first, always
Roof, flashing, windows and doors before anything decorative. Every finish inside depends on the building being dry, and there is no order in which that stops being true.
See this in a finished kitchen
A whole-home renovation is not many small jobs bought at once. It is one sequence, planned in an order that keeps the house standing up and keeps you living in it.
The house was built for somebody else, decades ago, with different assumptions about how many people would be in it and what they would be doing. A whole-home renovation is not an upgrade - it is the point at which the building finally matches the people in it. It is also the largest disruption a family will voluntarily invite into their own home, which is why the plan matters more than any finish in it.
This is the only job on the site photographed properly at both ends, and it is the one we would point at first. The roof was stripped to bare sheathing rather than layered over, which is the decision that separates a roof that lasts from one that is sold cheaply: you cannot inspect what you cover, and a second layer hides every soft spot underneath it. The new bundles were staged on the roof before the tear-off began, so the house was open for hours rather than days. The finished photograph is taken from the deck of the same house, which is back in use.
Roof, flashing, windows and doors before anything decorative. Every finish inside depends on the building being dry, and there is no order in which that stops being true.
See this in a finished kitchenOne flooring material carried across the whole level, without a threshold at every doorway, is the single change that makes a chopped-up house read as one house.
See this in a finished kitchenUsually one or two walls, not many. Which ones can move is a structural question we answer before it becomes a design one.
See this in a finished kitchenSequenced in zones so the house always has a working kitchen or a working bathroom - rarely both under construction at once, and never without telling you which weeks those are.
See this in a finished kitchenWhat the house gets wrong, how long you plan to stay in it, and what the budget actually is. Whole-home scope is decided here.
Roof, crawlspace, panel, and every room. On a renovation this size the surprises are structural, and they are cheaper to find now.
In writing, and phased - so you can see what happens in which month, and which rooms are out of use when.
Envelope, then rough trades, then floors, then rooms. Changing the order is how a renovation doubles in length.
Room by room as they finish, not all at the end - so the house becomes liveable again in stages rather than on one distant date.
Usually yes, and most families do. It depends on sequencing rather than on luck: we work in zones so there is a functioning kitchen or a functioning bathroom at almost every point, and we tell you in advance which weeks are the hard ones so you can plan around them.
Months rather than weeks, and the honest range depends entirely on scope and on what the walls turn out to be hiding. We would rather give you a phased schedule after walking the house than a number on the phone that we both know is a guess.
Because every finish inside depends on the building being dry, and because a roof replaced after the floors go down means covering new work or redoing it. The envelope is not the exciting part and it is not negotiable as a starting point.
Not everything and not all at once. We work room by room where the scope allows, and we will tell you what needs to be out of a space before we start on it rather than on the morning we arrive.
On a house-wide job something is always found - old wiring, a soft subfloor, a roof that has been patched rather than replaced. We show you, price it, and get your decision in writing before we carry on. Nothing gets buried and nothing gets billed as a surprise.
Yes, and for a lot of families that is the sensible answer. The thing worth planning centrally is the order - doing the envelope in phase one protects everything you spend in phases two and three.
Often part of the same job Kitchen Remodeling Bathroom Remodeling
No obligation and no sales visit. We will look at the room, tell you what it involves, and put a number in writing.